Optimasi Penjadwalan Proyek Perkerasan Jalan Lentur Jalan Konektor POLINELA Menggunakan Critical Path Method berbasis Microsoft Project 2021

Authors

  • Resti Agustina Politeknik Negeri Lampung

DOI:

https://doi.org/10.55606/isaintek.v9i1.401

Keywords:

Project Scheduling, Flexible Pavement, Microsoft Project 2021, Critical Path Method, Conector Road

Abstract

The area and distance between buildings at POLINELA Campus make the presence of adequate connector roads an important necessity to support the mobility of the academic community. This study aims to optimize the scheduling of flexible pavement construction for the POLINELA Connector Road using the Critical Path Method (CPM) based on Microsoft Project 2021. The research method used is descriptive quantitative by processing the Budget Plan (RAB) data into a project schedule consisting of 11 main activities. CPM analysis is used to determine the sequence of work, dependencies between activities, the critical path, and project completion time. The results show that the total project duration is 23 calendar days (May 11–June 6, 2026). CPM analysis identified 10 activities on the critical path with zero float, while embankment work is a non-critical activity with time flexibility. Applying a Start-to-Start (SS) relationship with a 3-day lag between excavation and embankment work allows parallel implementation, reducing the project duration by 4 days (14.8%) compared to the conventional Finish-to-Start (FS) scenario. These results indicate that implementing CPM through Microsoft Project 2021 can increase execution time efficiency, simplify schedule control, and support decision-making in road construction project management.

References

Agustiar, I., & Handrianto, R. (2018). Evaluasi penjadwalan proyek menggunakan metode cpm dan kurva s (Studi Kasus : Pembangunan Gedung Perpustakaan SMK N 1 “XX”, Gresik). Jurnal Keilmuan Dan Terapan Teknik, 07(02), 99–105. DOI : 10.5281/zenodo.3634238

Alviani, E., Putra, A. D., Siregar, A. M., & Usman, K. (2023). Manajemen Penjadwalan Menggunakan Microsoft Project dan Analisis Risiko pada Proyek Pembangunan RSPTN Universitas Lampung. JRSDD, 11(2), 255–264. DOI: 10.23960/jrsdd.v11i2.3130

Dewi, N. P. K., Sunatha, I. G. N., Duputera, I. G. A., & Hermawan, I. P. Y. (2023). Analisis perbandingan waktu rencana pelaksanaan proyek metode konvensional dengan metode cpm berbasis ms . Project ( Studi Kasus : Proyek Pembangunan Gedung KIA RSUP Prof . Dr . I . G . N . G Ngoerah ). Jurnal Ilmiah Teknik Unmas, 3(2). DOI: 10.5281/zenodo.10077300

Ferdiansyah, B. V., Setyaning, L. B., & Aziz, U. A. (2024). Jurnal Anggapa Analisis Penjadwalan Proyek Dan Rencana Anggaran Biaya ( RAB ) Dengan Critical Path Method ( CPM ) Studi Kasus : Proyek Pelebaran Jalan Ayah – Jladri Paket 2. Anggapa, 3(November), 1–10. DOI: 10.61293/anggapa.v3i2.737

Iriyanto, S. M., & Rarung, A. Y. (2019). Analisa efektivitas penjadwalan proyek rumah susun papua 1 dengan metode pert. Portal Sipil, 8(2), 1–11. https://ojs.ustj.ac.id/sipil/article/view/590

Isnubroto, D., Parmasari, D. H., Hadi, T., Mulyono, T., Ariyanto, A. S., Studi, P., Sipil, T., Semarang, P. N., Studi, P., Masyarakat, K., Soedirman, U. J., & Project, M. (2024). Analisis penjadwalan proyek menggunakan metode cpm dan program bantu microsoft project. Journal of Research and Technology Studies, 03(1), 30–38. DOI: 10.33096/jtsm.v9i2.800

Isnubroto, D., & Putri, C. K. (2021). pada proyek konstruksi menggunakan microsoft project ( Studi Kasus Pekerjaan Struktur Proyek XYZ ). Wahana TEKNIK SIPIL, 26(1), 52–65. DOI: 10.32497/wahanats.v26i1.2647

Kadir, D. M. (2024). Estimasi biaya dan waktu pelaksanaan pembangunan jalan kalaodi - fobaharu di kota tidore kepulauan. AKRAB JUARA, 9(1), 30–40. DOI: 10.58487/akrabjuara.v9i1.2305

Khotimah, I. H., Rodhi, N. N., & Tjandra, A. (2024). Analisis Pengendalian Waktu Proyek Menggunakan Metode Critical Path Method ( CPM ) ( Studi Kasus : Proyek Rehabilitasi Jalan Dander - Bubulan ) De ’ Teksi : Jurnal Teknik Sipil. De’Teksi : Jurnal Teknik Sipil, 9(2), 60–69.

Mantovani, M. R., Beatrix, M., & Teknik, F. (2023). Evaluasi pengendalian biaya dengan metode critical path method ( cpm ) menggunakan microsoft project ( studi kasus : pekerjaan tahap vii proyek perkuatan struktur dermaga berlian tanjung perak surabaya). Jurnal Taguchi: Jurnal Ilmiah Teknik Dan Manajemen Industri, 3(1), 721–732. DOI: 10.46306/tgc.v3i1.122

Mar’Aini, & Akbar, Y. R. (2022). Penentuan Jalur Kritis untuk Manajemen Proyek ( Studi Kasus Pembangunan Jalan Selensen- Kota Baru- Bagan Jaya ). Jurnal Pustaka Manajemen, 2(2), 6–13. DOI: 10.55382/jurnalpustakamanajemen.v2i1.184

Mirnayani, R. A., Suwandari, Y. D., & Lutfiansyah, Y. (2025). Pelatihan Tukang Dalam membuat Campuran Beton Untuk Bangunan Rumah Ramah Gempa. 9(1), 15–22.

Paramitha, N. G., & Barata, F. A. (2026). Analisis Manajemen Waktu Dengan Metode CPM Pada Proyek Rekonstruksi Ruas Jalan Soekarno Hatta Kabupaten Lamongan , Jawa Timur. PESHUM : Jurnal Pendidikan, Sosial Dan Humaniora, 5(3), 6890–6897. DOI: 10.56799/peshum.v5i3.14986

Prabowo, Y. S., & Hofifah, S. (2025). Penggunaan navisworks manage dan ms. Project untuk monitoring penjadwalan proyek konstruksi. Syntax Literture : Jurnal Ilmiah Indonesia, 10(5), 5460–5471.

Rahmawati, R., Isnubroto, D., Hadi, T., Ariyanto, A. S., & Wahjoedi, S. (2024). Pelatihan penjadwalan proyek menggunakan ms project di pt geo dipa energi (PERSERO) TBK. SENTRIKOM, 6, 251–259.

Resta, M. B. (2023). Optimasi biaya & waktu pada penjadwalan proyek perumahan dengan microsoft project (Studi kasus : Perumahan Cluster Pamulang) Muhammad. Salome: Multidisipliner Keilmuan, 1(4), 295–306. DOI: 10.61293/salome.v1i4.295 (doi.org in Bing)

Saputra, R. B., Khamid, A., Diantoro, W., & Apriliano, D. D. (2021). Studi Perencanaan Perkerasan Lentur Jalan pada Ruas Jalan Balapulang – Pagerbarang Kabupaten Tegal Study of Road Flexural Pavement Planning on Balapulang – Pagerbarang Road Tegal Regency. Infratech Building Journal (IJB), 2(2), 68–79. DOI: 10.46772/ibj.v2i2.786

Setiawati, S., & Ariessa, R. (2016). Penerapan Metode CPM Dan PERT Pada Penjadwalan Proyek Konstruksi ( Studi Kasus : Rehabilitasi / Perbaikan Dan Peningkatan Infrastruktur Irigasi Daerah Lintas Kabupaten / Kota D . I Pekan Dolok ). Repositori Institusi Universitas Sumatera Utara, 1–14. https://repositori.usu.ac.id/handle/123456789/80694

Sulistyo, A. B., & Fikri, M. Al. (2021). Proyek konstruksi menggunakan metode time cost trade off ( studi kasus : proyek pembangunan jalan gorda-bandung ). Jurnal InTent, 4(1), 25–40. DOI: 10.36085/intent.v4i1.1400

Sunatha, I. G. N., Diputera, I. G. A., & Hermawan, I. P. Y. (2023). Analisis rasio biaya sumber daya rencana dan realisasi menggunakan microsoft project ( Studi Kasus : Kegiatan Pembangunan Jalan Pantai Pererenan ). Jurnal Ilmiah Kurva Teknik, 12(2), 166–173. DOI: 10.36733/jikt.v12i2.7860

Sunatha, I. G. N., Praganingrum, T. I., Pradnyadari, N. L. M. ayu M., & Atama, J. W. (2022). Analisis evaluasi dan monitoring pelaksanaan proyek menggunakan metode tracking berbasis microsoft project pada. Jurnal Ilmiah Kurva Teknik, 11(1), 16–24. DOI: 10.36733/jikt.v11i1.3930

Downloads

Published

2026-06-26

How to Cite

Agustina, R. (2026). Optimasi Penjadwalan Proyek Perkerasan Jalan Lentur Jalan Konektor POLINELA Menggunakan Critical Path Method berbasis Microsoft Project 2021 . Jurnal Informasi, Sains Dan Teknologi, 9(1), 89–103. https://doi.org/10.55606/isaintek.v9i1.401

Similar Articles

<< < 1 2 3 4 5 > >> 

You may also start an advanced similarity search for this article.